top of page
vaxa_logo_FF0000_transparent.png
LET'S TALK
vaxa_logo_FF0000_transparent.png
LET'S TALK
Site Selection Used to Be a Real Estate Decision. It Is Now a Board-Level One.

Market Intelligence

Vaxa ON

Published on June 24, 2026

3 min Read

Digital Infrastructure

Site Selection Used to Be a Real Estate Decision. It Is Now a Board-Level One.

In 2026, site readiness is a spectrum defined by power certainty, entitlement risk, delivery sequencing, and political exposure — all at once. This is now a board-level risk, not a site-selection footnote.

Vaxa Service:

Related Service:

By Vaxa Strategy Team

HIGHLIGHTS

~100 GW of new data center capacity expected globally between 2026 and 2030 — nearly doubling today's installed base

$3T in combined real estate, fit-out, and IT investment projected through 2030

140+ local community groups now mobilized against hyperscale data center projects across the U.S.

$30B project canceled by QTS in 2026 — a signal of how execution risk is repricing the sector

SECTOR CONSENSUS

Data center site selection is a real estate decision — find land near fiber and population centers, confirm power as a checklist item, build.

VAXA POSITION

Site readiness in 2026 is a spectrum defined by power certainty, entitlement risk, delivery sequencing, and political exposure all at once — and this is now a board-level risk, not a site-selection footnote.

The Shift

Site selection used to be a real estate decision. It is now a board-level one.

For most of the past two decades, data center site selection followed a familiar playbook: find land near fiber routes and population centers, negotiate tax incentives, confirm power availability as a checklist item, and build. Power access was assumed. The harder questions were about connectivity, climate, and cost.

That playbook no longer applies. In 2026, site readiness is not a binary condition — it is a spectrum defined by power certainty, entitlement risk, delivery sequencing, and political exposure, all at once. Developers are restructuring real estate strategy around energy strategy from the outset, not after a site is chosen. Power access is no longer a feasibility check. It is the foundation of the investment case.

The scale of capital now committed to this buildout means these are no longer operating decisions delegated to real estate and infrastructure teams. A five-year delay on a hyperscale project erodes competitive positioning, compresses IRR, and can cost an operator an enterprise contract to a faster-moving competitor. That is a board-level risk, not a site-selection footnote.

Bar chart showing only 13% of interconnection requests reached commercial operation while 87% were withdrawn, stalled, or still pending

Power as the Bottleneck

Interconnection, not land, is now the pacing item.

Nearly two terawatts of generation capacity are currently stuck in U.S. interconnection queues — almost twice the country's installed base. PJM, the largest grid operator in the country, reopened its queue in 2026 after a multi-year pause, having accumulated a backlog exceeding 300 gigawatts of projects. ERCOT's Large Load interconnection process now has more than 225 gigawatts of large loads moving through it, prompting the grid operator to bring in outside help to redesign the process.

In response, developers are restructuring deployment plans around certainty rather than cost. Behind-the-meter generation, battery storage, and hybrid power strategies are increasingly built into project planning from day one, despite the higher upfront capital they require. A decade ago, developers optimized for the lowest delivered cost. In 2026, they are optimizing for the earliest energization date — because a five-year wait for grid access is now a bigger threat to a project than a modest cost premium.

This has cascaded into the labor market as well. Gas and combined-cycle generation expertise is resurging, battery storage and microgrid capability are in sustained demand, and utility relationship management — once a peripheral function — has become a core commercial capability for any operator building at scale.

The trend is accelerating, not stabilizing. Data center cancellations more than quadrupled from 6 in 2024 to 25 in 2025, and one industry tracker found that a quarter of the projects planned for 2026 haven't even disclosed a powering strategy — a direct sign that site selection is still happening before power access is confirmed, on exactly the sequence this piece argues has inverted. In early 2026, Oracle and OpenAI terminated a planned expansion of their flagship Abilene, Texas campus from 1.2 to 2.0 gigawatts, citing financing challenges and shifting energy infrastructure forecasts — a live, current example, not a historical one.

Bar chart showing the U.S. grid interconnection queue growing from 1,400 GW (2021) to 2,000 GW (2024) to 2,600 GW (2025-26)

Regulatory and Political Risk

Water, foreign ownership, and local opposition are now underwriting variables.

Power is no longer the only gatekeeper. Water availability has become a second, equally binding constraint — a data center project can clear every power and permitting hurdle and still be halted over water. Several jurisdictions have introduced consumptive-use permitting frameworks specifically for large-load data centers, and at least one major project has already been stopped over water permitting despite having secured local approvals.

State legislatures are also moving faster than the industry's planning cycles can absorb. New restrictions now require full cost-of-service accounting for large-load customers, and some states have gone further, barring utilities from serving foreign-controlled large-load customers altogether. New York's own one-year moratorium on new hyperscale permitting, driven by ratepayer electricity costs rather than power availability, is part of the same pattern — regulatory risk is compounding independently of grid capacity.

Local opposition has become organized enough to change outcomes, not just optics. More than 140 community groups have mobilized against hyperscale projects nationally. Ballot measures, council turnover, and federal environmental litigation are now realistic outcomes of a contested site — not tail risks. For developers underwriting a project, community and political risk now sit alongside power and water as line items, not afterthoughts.

Bar chart showing interconnection timelines stretching from 1-3 years pre-pandemic to 5-8 years now

What This Means for Strategy

Speed and certainty now outrank marginal cost.

The practical consequence for site selection teams is that the old sequence — find the site, then solve for power — has inverted. Power and water certainty now come first, because they determine whether a site is viable at all before real estate economics are even relevant. Regulatory and community risk assessment has to happen in parallel, not after entitlement, because a state legislative session or a local ballot measure can invalidate months of site work overnight.

For operators, this means site selection can no longer be owned solely by real estate and infrastructure teams — it requires the same rigor applied to political, regulatory, and utility relationship risk that used to be reserved for market entry decisions in regulated industries. For investors and boards, it means underwriting models built on delivered cost and land economics are missing the variable that is actually determining outcomes in 2026: schedule certainty.

The operators who treat this as a portfolio-level capability — tracking interconnection queues, water permitting frameworks, and state legislative activity the way they'd track any other market intelligence — will out-execute the ones still treating site selection as a real estate function with a power checklist attached.

The Big Takeaway

01

Power certainty, not land, is now the first gate a site has to clear.

02

Only 13% of interconnection requests filed 2000-2019 reached commercial operation by 2024.

03

Water and political risk are now independent, binding constraints, not secondary checklist items.

04

Cancellations are accelerating — 2 (2023) to 25 (2025) — a repricing signal, not noise.

05

Underwriting models built on delivered cost and land economics are missing the variable that actually decides outcomes: schedule certainty.

closing question

Is your site selection process still organized around real estate and cost — or has it been rebuilt around power certainty, water risk, and political exposure as the primary variables?

Vaxa On tracks power, water, and regulatory signals across states continuously, giving site selection teams a live read instead of a point-in-time study.

References

Lawrence Berkeley National Laboratory, interconnection queue and completion-rate research

bottom of page